Renovating a bathroom

A new bathroom follows a fixed order: first demolition and pipes, then the walls and floor, then tiles and finally the sanitary ware. If one step in the planning goes wrong, the rest stands still.

Prices incl. VAT for a bathroom of 4 to 6 m² with shower, toilet and washbasin. Checked in 11-2026.

Your plan

  1. 1. Demolition and disposal

    Old tiles, sanitary ware and pipes out, rubble removed.

    aannemer · 2 days

    € 800 – € 2,000Request quotes
  2. 2. Pipes and drainage

    New water and drain pipes where the new sanitary ware goes.

    loodgieter · 2 days

    € 1,200 – € 3,000Request quotes
  3. 3. Electrics and ventilation

    Circuit for the bathroom, sockets, lighting and the extractor fan.

    elektricien · 1 day

    € 500 – € 1,500Request quotes
  4. 4. Preparing walls and floor

    Making walls flat, levelling the floor and waterproofing it.

    stukadoor · 2 days · then wait 7 days (drying)

    € 800 – € 2,000Request quotes
  5. 5. Tiling

    Setting and grouting wall and floor tiles.

    tegelzetter · 5 days · then wait 2 days (drying) · costs in detail

    € 2,000 – € 5,000Request quotes
  6. 6. Fitting sanitary ware

    Connecting and sealing the toilet, washbasin, shower and taps.

    badkamerspecialist · 2 days · costs in detail

    € 1,500 – € 6,000Request quotes
  7. 7. Ceiling and finishing(if needed)

    Painting the ceiling with moisture-resistant paint, lacquering the door and frame.

    schilder · 1 day

    € 300 – € 900

Total about € 6,800 to € 19,500, 6 steps

Permit

For a bathroom inside your home you usually don't need a permit. Living in an apartment? Then ask the owners' association for permission if you change pipes or the floor.

Check it in the Omgevingsloket

Tips

  • Choose tiles and sanitary ware before you ask for quotes: delivery often takes 2 to 6 weeks.
  • Have one company make the planning if you have several pros, or choose a bathroom specialist who arranges everything.
  • Agree who removes the rubble and who arranges the skip.